The construction of 4-laning of the Project between Galgalia – Bahadurganj having total length of 49 km has been awarded to M/s GR Infra Projects Highway Ltd. The appointed date of this project is 10.01.2022. At present physical progress is 70%.
An unexpected settlement of 600 mm (approx.) occurred on 23.06.2023 afternoon at the pile foundation beneath pier P3 on Major Bridge at CH 24+461 having span configuration of 1x20m + 5x36m + 1x20m (total length 222 m) with PSC girder superstructure resting over spherical bearings on an RCC circular column and pile foundation consisting of four piles of 1500 mm diameter. The superstructure was erected in May 2023 and the Bridge is not yet in operation. There is no casualty or injuries to any construction workers.
Preliminary investigation reveals that recently there is sudden rise of water flow from Nepal in Meachi river on which this bridge is constructed. Further preliminary investigations have also revealed that the entire river was channelized through the P2-P3-P4 spans during the construction activity, leading to the constriction of water flow and excessive scour of the sandy river bed. This has possibly contributed to the settlement of the pile foundation at P3.
Team of NHAI officers, the Concessionaire and Independent Engineer reached at site and taking necessary preliminary rectification work to avoid any further settlement in pile foundation at P3.
In the meantime, Team Leader & Bridge Engineer of Independent Engineer, M/s Chaitanya Project Consultancy Pvt. Ltd. and Sr. Project Manager & Dy. Project Manager (Structure) of Concessionaire, M/s GR Galgalia Bahadurganj Highway Private Limited have been suspended with immediate effect to avoid any influence on the ongoing investigation.
Further, a Committee of experts comprising of (i) Sh. A. K. Shrivastava, ADG (Retd), MoRTH (ii) Sh. S. K. Sharma, Pr. Tech. Officer – Bridges (Retd.), CRRI and (iii) Sh. Venkatram P. G., M/s L&T Infrastructure Engineering Limited has been constituted & is scheduled to visit the site today for detailed investigation and ascertain cause of settlement of pile foundation at P3 on Major Bridge at CH 24+461 and consequent remedial measures to be undertaken.




6 Responses
Your article helped me a lot, is there any more related content? Thanks! https://www.binance.bh/register?ref=IXBIAFVY
I don’t think the title of your article matches the content lol. Just kidding, mainly because I had some doubts after reading the article.
Здесь сайте можно почерпнуть полезную информацию.
https://moizvezdi.ru/stars/2026-07-17-kak-podobrat-krossovki-liu-jo-pod-raznyy-stil-odezhdy/
На этом ресурсе вы сможете почерпнуть важную информацию.
https://rosotels.ru/detail/2026-07-16-ukraina-i-devyat-evropeyskikh-gosudarstv-obedinyayutsya-v-antiballisticheskuyu-koalitsiyu-posledstviya-dlya-rossii.htm
Продвижение сайтов — это комплекс действий, нацеленных на повышение позиций в поисковых системах.
Главная цель такого продвижения — поднять веб-ресурс в верхние позиции поисковой выдачи по нужным запросам.
http://prodvizhenie-saytov-moskva.ru/
Чтобы достичь такого результата оптимизаторы выполняют технический аудит, трудятся над содержанием, архитектурой и ссылочным профилем.
Благодаря этому сайт становится заметнее в поиске, получает значительно больше целевого трафика и повышает конверсию.
Ресурсы взрослой направленности призваны служить способом интимного просвещения, а также помощью в осознании собственных желаний.
Такие площадки позволяют пользователям исследовать свои фантазии в контролируемой форме, снижая риски реальных последствий.
ero-storitop.com
Для пар взаимное ознакомление таких тем может усиливать взаимопонимание и служить стимулом для открытого диалога о желаниях и границах.
Помимо этого такие платформы предоставляют шанс для безрисковой реализации напряжения и снятия психологического напряжения, не причиняя ущерба окружающим.